| Classroom Presentation Systems |
Status |
|
On target to get an LCD projector into every classroom in 2009-10 school year. |
|
We mount projectors as quickly as we can, with a goal of having each year’s purchases mounted by winter break. |
|
Classroom Benefits:
|
|
| PC/Server Refresh |
Status |
| Over time, software updates demand increased hardware performance. At the same time, aging hardware becomes less reliable and requires additional maintenance (and people to provide that support). We have adopted a plan for scheduled replacement over a 3-4 year (ongoing) time-frame (i.e. 1/4 to1/3 of all devices replaced every year). This compares to our current 20% annual replacement. Our estimate is based on purchasing. Key elements of this include: | We have been replacing older machines and expect to be fully on this cycle with the start of the 2008-09 school year. |
|
Done (effective 8/15/2007) |
|
Done. However, our analysis of problems reported indicates that this isn’t needed for desktop machines and we’ve switched to ordering those with basic one-year warranty. |
|
Done (effective 8/15/2007) |
|
We’ve added servers and started replacing older ones. We expect to be fully on this cycle with the start of the 2008-09 school year. |
Classroom Benefits:
|
|
| Wireless Access Points |
Status |
| Provide wireless access throughout each facility as well as on playgrounds and sport fields (for phone access in order to deal with emergency situations). | We have started to implement ubiquitous wireless in school buildings that have been re-wired. This does not yet include exterior access, which may be better handled via alternate methods. |
Classroom Benefits:
|
|
| Student/Financial Record-Keeping Software |
Status |
| Student Records
|
We have purchased and are implementing Skyward effective with the 2007-08 school year. Not all functionality will be available on day one. As soon as practical, we’ll start to implement the parent portal and will add features to it as they are implemented. |
| Financial Records
|
In December, 2007 the Board approved the contract for the IFAS software from Sungard Bi-Tech. Implementation will be phased, and is expected to take 12-18 months to complete. |
| Classroom Benefits:
|
|
| Expand Storage Area Network (SAN) Improve Disaster Recover (DR) Capability |
Status |
| Our previous storage device did not accommodate all of our storage needs and was still at 97% of capacity (where 90% would be considered “critical” and 80% “high”). Key objectives are: | Ongoing – we regularly evaluate the use and adequacy of network storage. |
|
SAN expanded from 2TB to 30TB. |
|
Initial objectives met. |
|
Initial objectives met. |
|
“Bare bones” backup SAN purchased and in use – will be expanded when DR site is built (targeted for 07/08 school year) |
| Classroom Benefits:
|
|
| Network Management |
Status |
| A strong, centrally managed network is key to providing district-wide computer service and to cost-effectively managing that environment. As such, it is paramount that the network be reliable, easy to manage and well-monitored. Items to be improved include: | Ongoing – we constantly work to improve network reliability. |
|
Ongoing. We continue to evaluate tools to address specific monitoring needs. |
|
LanDesk was implemented at the start of the 07/08 school year. We're in the process of removing Novell Desktop from client machines. |
| Classroom Benefits:
|
|